Questions on the EU Methane Regulation,
answered.
What Regulation (EU) 2024/1787 requires from gas network operators, and how EMRES helps. Each answer cites its article.
REGULATION
Who does Regulation (EU) 2024/1787 apply to?−
It applies to oil and gas exploration and production, gas transmission, distribution, underground storage and LNG terminals, inactive and abandoned wells, coal mines, and importers of oil, gas and coal (Art. 1). For gas network operators, the core obligations are monitoring and reporting (Art. 12), leak detection and repair (Art. 14), and venting and flaring (Art. 15 to 17).
Read more →What are the key deadlines for gas network operators?+
For existing sites and operated assets: LDAR programme by 5 May 2025, first type 2 LDAR survey and first emissions report by 5 August 2025, source-level quantification, venting and flaring restrictions and compliant flares by 5 February 2026, site-level measurements by 5 February 2027, then an annual report by 31 May every year.
Read more →What are the penalties for non-compliance?+
Penalties are set by each Member State. For legal persons, administrative fines cannot exceed 20% of the previous year's annual turnover (Art. 33).
Read more →Does the Regulation require OGMP 2.0 Level 5?+
No. It does not use OGMP 2.0 levels, but its requirements broadly correspond to Levels 4 and 5. It does refer to OGMP 2.0: until the Commission adopts its own reporting template, operators use the OGMP 2.0 guidance and reporting templates (Art. 12(4) and (5)).
Read more →LEAK DETECTION AND REPAIR
What is the deadline to repair a methane leak?+
Leaks above the Art. 14(8) thresholds must be repaired immediately after detection. If that is not possible, a first attempt is made within 5 days and the repair is completed within 30 days. If the operator can show this is not possible, it notifies the competent authority within 12 days of detection, with evidence and a repair and monitoring schedule. Repaired components are checked again no later than 45 days after the repair (Art. 14(9) and (12)).
Read more →What is the difference between a type 1 and a type 2 LDAR survey?+
They differ by the leak size that must be repaired and by their frequency. Type 1: 7,000 ppm or 17 g/h of methane. Type 2: 500 ppm or 1 g/h for above-ground components, and 1,000 ppm or 5 g/h at the second step for underground components (Art. 14(8)). Minimum frequencies are set in Annex I.
Read more →How does LDAR work on an underground distribution network?+
In two steps: first at the interface between the ground and the air, then, once a leak is detected, as close as possible to the source (Art. 14(6)). For transmission and distribution networks, Annex I sets frequencies by pipe material and design pressure (above or up to 16 bar). EMRES plans and tracks these surveys by kilometre of network.
Read more →MEASUREMENT AND REPORTING
What is the difference between source-level and site-level measurement?+
Source-level quantification estimates emissions source by source (components, equipment, events), bottom-up. Site-level measurement measures the whole site independently, top-down, for example by vehicle, drone or aircraft. Art. 12 requires both for operated assets.
Read more →How are source-level and site-level emissions reconciled?+
Art. 12(6) requires operators to compare the two. If the gap is statistically significant, they notify the competent authority before the end of the reporting period, then run a reconciliation and report its results, with evidence, by the next reporting period. The text sets what the reconciliation must look at, not a single method.
Read more →When must venting and flaring events be notified?+
Events caused by an emergency or a malfunction, or lasting 8 hours or more within 24 hours, are notified to the competent authority within 48 hours (Art. 16(1), Annex III). All events are also included in the annual Art. 12 report.
Read more →Who verifies the emissions report, and what do they check?+
Before submission, the report must be assessed by an independent verifier, accredited under Art. 9, and include a verification statement (Art. 8 and 12(3)). In practice, verifiers look for traceability from each figure back to its measurement, method and sign-off.
Read more →ABOUT EMRES
Can we keep our existing tools and our OGMP 2.0 reporting?+
Yes. EMRES works on top of your existing tools: asset registers, GIS, maintenance data and contractor results feed the same record, and the OGMP 2.0 report is produced alongside the EU template.
Read more →Can LDAR contractors use EMRES for several operators?+
Yes. Contractors get their own workspace, connected to each client's EMRES, with each client kept separate. Survey results and evidence go straight into the client's register.
Read more →Does the field app work without network coverage?+
Yes. The EMRES field app works offline on ATEX-certified devices and syncs to the platform automatically when the connection returns.
Read more →Where is EMRES data hosted, and in which languages is it available?+
Data is hosted in the European Union. The platform is available in more than seven languages, with support in English, French and Dutch.
Read more →Can we test EMRES on our own data?+
Yes. After a 30-minute demo, we can set up a pilot on part of your data in a secure test environment.
Read more →